October
2003 Consent Order and Agreement
In October 2003, Millcreek and the Millcreek Township Sewer Authority
entered into a Consent Order and Agreement (COA) with the Pennsylvania
Department of Environmental Protection (PaDEP) to resolve issues relating to
operations of the sanitary sewer system, particularly near the Kearsarge Sewer
Station.
In 1992, the Township and the Sewer Authority entered into a COA which
called for a variety of improvements to the sanitary sewer system, all of which
had been completed before 2003. The ultimate objective of the 1992 COA was to
make improvements to the system that would result at a later date in termination
of the bypass which has discharged sanitary sewerage into Walnut Creek. The
bypass was created years ago to protect homes in the Kearsarge area from backups
of sewage when the capacity of the sewer system was being exceeded. This
situation generally arose after storm events when substantial volumes of storm
water have infiltrated the sanitary sewer system.
Projects to address obligations under the 1992 COA included the flood
detention basin near Chestnut Hill School, storm sewer upgrades in the Kearsarge
area, projects to dredge and increase the capacity of Beaver Run Creek and a
major upgrade in sewer lines down Pittsburgh Avenue.
All of these projects were completed.
Advances in technology since the early 1990' s enable a sewer system to
better identify volumes and sources of stormwater flows into the sanitary sewer
system. Improvements called for in
the 1992 COA were designed and approved before the extent of infiltration of
storm water through unlawful connections to the sewer system was known.
With better technology, the extent and impact of flows of storm water
into the sanitary sewer system could be detected.
By 2003, Millcreek and the Authority recognized that, on average, about
25% of flows in the sanitary sewer system are storm water and that this
percentage dramatically increases after storm events. The principal source of
these storm water flows is unlawful connections of storm water discharge into
the sanitary sewer, from sump pumps, downspouts, floor drains and the like.
The October 2003 COA prescribed action intended to terminate the
Kearsarge bypass. The Township and
the Sewer Authority committed themselves to improvements which would increase
capacity of the Kearsarge Sewer Station. Improvements
to the Station were made. Two large
retention facilities were constructed to retain sanitary flows after storm
events until the system could properly convey them.
Capital improvements could only do so much.
The significant flows of clean or storm water into the sanitary sewer
system did not simply overwhelm the system’s capacity after storm events.
There is no need to treat storm water. When
it is connected to the sanitary system, it ends up being conveyed to the sewage
treatment plant for treatment - and users of the system pay substantial costs
for that - hundreds of thousands of dollars each year.
Recognizing that only reduction in flows of clean water into the system
could ensure that it can operate as designed and that the status quo was costing
system users a lot of money, the Millcreek and the Authority, in the 2003 COA,
committed to establishing a program to terminate unlawful connections of clean
water into the sanitary sewer system. That
system was put in place in early 2004 and continues.
All improvements required by the COA were completed promptly.
The Kearsarge bypass was terminated in March 2007.
No discharges into Walnut Creek have occurred since the retention
facilities were completed. In 2009,
the PaDEP approved termination of limits on new connections under the 2003 COA
because their objectives had been met. In
addition, termination of clean water flows into the system has significantly
reduced incidents of backups in homes and flows in the sanitary sewer system
generally.